OutcomeApproved by the Board of County Commissioners on Oct 25, 2022
Approved the Public Hearing Consent Agenda which included Agenda items P85, P86, P87, P88, P89 including ex-partes that had been submitted to the Clerk’s Office and the addition of Condition 31, P90, and P91.

Official title

Roadway Transfer Agreement (Consent) – Florida Department of Transportation – State Road 54A/Black Lake Road from State Road 54 Western Connection to State Road 54A/Black Lake Road Cul-De-Sac and State Road 54 Eastern Connection – No Funding Required

Every appearance1 of 1 are in a recording

TranscriptWhat was said at each appearance is below it. Machine transcription, with speaker names inferred from voice matching. 33% of 9 lines carry a name. It shows what was said, not what was decided, and both the words and the names can be wrong.

  1. 1
    Board of County CommissionersP85Public hearingApproved
    Approved minutes

    Approved the Public Hearing Consent Agenda which included Agenda items P85, P86, P87, P88, P89 including ex-partes that had been submitted to the Clerk’s Office and the addition of Condition 31, P90, and P91.

    Open this item →
    3m
    StarkeyChair

    so P eighty five. And are we Now at

    Unidentified speakerVoice A

    If you want me to do the procedures, we can do that now. Uh there are two rezoning agendas, regular and consent. Staff will present each application to the Board of County Commissioners. If staff or planning commission has recommended approval and there is no opposition, the application will be considered by the Board of County Commissioners without further presentation. If the staff or planning commission Uh has recommended denial, or if there is opposition to the application, the applicant will be given five minutes. For

    presentation, the opposition will be given three minutes for each individual or five minutes for a group representative and the applicant will be given three minutes for rebuttal. Any individual disagreeing with staff or planning commission recommendation or anyone wishing to object to any condition of the rezoning may at this time request the petition be pulled. on the consent agenda, in which case that application will be heard under the regular agenda later on during the meeting. Otherwise all rezoning applications on the consent agenda will be approved by a single motion and vote.

    If you wish to speak to any petition, please give your name and address and whether or not you've been sworn for the record. These are quasi-judicial public hearing. The law in Florida is mere public support or opposition of an application is insufficient for this board to take action. Please limit your comments to those criteria found within the board's land development code. Madam Clerk, do you wish to square them in?

    Unidentified speakerVoice B

    I would. Um if you are here to speak on any of the remaining items, please stand. If you're able to and raise your right hands.

    Do you swear or affirm the testimony you're about to give is the truth, so help you God. Thank you.

    Okay, let's go with the first one, P eighty-five. Item P eighty five was published in the Tampa Times on October 9, 2022.

    Oakley

    Item P A eighty-five is a roadway transfer agreement uh Florida by the Florida with the Florida Department of Transportation, State Road 54A slash Black Lake Road from State Road 54 Western connection to State Road 54A slash Black Lake Road cul-de-sac. And say Road fifty four eastern connection.

    StarkeyChair

    Yeah, and we kind of found this out while we were working with a developer in in that area. So um it's kind of just a little oversight. Um is there anyone here to speak against this item? Do we have anyone signed up to speak against it? No one is signed