FAC-16-015
Published agenda2 appearances between Dec 15, 2015 and Jan 26, 2016.
OutcomeApproved by the Board of County Commissioners on Jan 26, 2016
Approved Consent Agenda
Official title
Change Order No. 1 to Task Order No. FM15-002 - Fleischman and Garcia Architects and Planners, AIA, PA - Fire Station No. 12, Engineered Fill Dirt Stock Pile: Extend Task Order 232 Days and Authorize Field Construction and Project Closeout Services - $3,080.00
On a calendar
Dec 15, 2015 → Jan 26, 2016 · click a mark to jump to that appearance
Every appearancenone of these are in a recording
Each appearance carries the official title above. Where the county’s wording changed, the change is marked: added and removed. Steps with no marks were worded identically.
- 1
Change Order No. 1 … Pile: Extend Task Order
23290 Days and Authorize Field … Closeout Services - $3,080.00Approved minutes
Withdrawn.
Open this item →No recording - 2
Approved minutes
Approved Consent Agenda
Open this item →No recording