Official title
Receive the Right-of-Way (ROW) Performance Guarantee Surety Bond No. 47- SUR-300244-01-0003 – Element Commercial Construction, LLC (Developer) – Lakepointe Parkway Road Improvements (Construction of Lakepointe Parkway Extension, Pavement Striping and Roadway Modifications for Additional Left Turn Lane on Lakepointe Parkway at the Intersection of State Road 54), Permit No. ROW-2024-00065 (TED24-0153)
On a calendar
Aug 6, 2024 → Sep 17, 2024 · click a mark to jump to that appearance
Every appearancenone of these are in a recording
Each appearance carries the official title above. Where the county’s wording changed, the change is marked: added and removed. Steps with no marks were worded identically.
- 1
Receive the Right-of-Way (ROW) Performance Guarantee Surety BondRevision No.47- SUR-300244-01-0003 – Element Commercial Construction, LLC (Developer) – Lakepointe Parkway Road Improvements (Construction of Lakepointe Parkway Extension, Pavement Striping and Roadway Modifications1 forAdditional Left Turn Lane on Lakepointe Parkway at the Intersection of State Road 54), PermitTask Order No.ROW-2024-00065 (TED24-0153)1-24 – JMG Engineering, Inc. – Design Review Services – Waste to Energy Expansion Design Build Project (SW24- 0335)Approved minutes
Approved as part of the Public Hearing Consent Agenda.