Published agendaHeard once, at the Board of County Commissioners on Dec 15, 2015.
OutcomeApproved by the Board of County Commissioners on Dec 15, 2015
Approved Staff's Recommendation with changes to Conditions 12a, 12b, and 19 regarding the Transit Shelter.
Official title
MPUD REQUEST (REGULAR) - FCI MPUD Master Planned Unit Development – Florida Citrus Investors, Inc. – Request a Substantial Modification to the MPUD - Located on the West Side of U.S. 41 at the Terminus of Keene Road, Which is Approximately One-Half Mile South of the Intersection of U.S. 41 and S.R. 52 (Parcel ID Nos. 16 25 18-0000-02000-0000, 16 25 18-0000-02200-0000, 17 25 18-0000-00200-0000, and 08 25 18-0000-00300-0010) and contains 160.045 acres, m.o.l.
Every appearancenone of these are in a recording
- 1
Approved minutes
Approved Staff's Recommendation with changes to Conditions 12a, 12b, and 19 regarding the Transit Shelter.
Open this item →No recording