PMA-23-0017
Published agendaHeard once, at the Board of County Commissioners on Dec 6, 2022.
Approved Staff’s recommendation to include the correction to the contract amount in the Change Order Agreement.
Official title
Change Order No. 3 to Professional Services Agreement – HDR Engineering, Inc. – Old Pasco Road Route Study and Pond Siting Analysis Report; from Wesley Chapel Boulevard (C.R. 54) to S.R. 52 – No Funding Required
Every appearance1 of 1 are in a recording
TranscriptWhat was said at each appearance is below it. Machine transcription, with speaker names inferred from voice matching. 100% of 6 lines carry a name. It shows what was said, not what was decided, and both the words and the names can be wrong.
- 1
Approved minutes
Approved Staff’s recommendation to include the correction to the contract amount in the Change Order Agreement.
under a minutePanos ConcesGood Good afternoon. Uh I'm Panos Conces, Assistant Engineering Services Director. Uh this item was pulled and revised because uh to correct the contract amount in the change order agreement. So the we circulated the new Uh change order.
Kathryn StarkeyChairMove to approve C sixty two. Second.
Panos ConcesAll
Jack MarianoVice Chairin favor say aye.
Kathryn StarkeyChairAye.
Jack MarianoVice ChairAny opposed? Thank you. And C sixty nine, Venkat. There he is.