UTD-20-0345
Published agendaHeard once, at the Board of County Commissioners on Jun 30, 2020.
Approved Staff’s recommendation including the revision to add a page to the letter of surety that was missing from SIRE by roll call vote.
Official title
Approve Construction Management at Risk (CMAR) Agreement and Pre- construction Services for RFP-CA-19-233 - Garney Companies, Inc. - Embassy Hills Wastewater Treatment Plant Rehabilitation and Improvements Project, PCU 16-014.00 - $585,000.00
Every appearance1 of 1 are in a recording
TranscriptWhat was said at each appearance is below it. Machine transcription, with speaker names inferred from voice matching. 80% of 5 lines carry a name. It shows what was said, not what was decided, and both the words and the names can be wrong.
- 1
Approved minutes
Approved Staff’s recommendation including the revision to add a page to the letter of surety that was missing from SIRE by roll call vote.
1mUnidentified speakerVoice Adifficult. Good morning, uh Commissioner Oak Charles Cullen. Uh Engineering. Contract management director for utilities. Item 73 is a construction manager at risk contract for Embassy Hills wastewater plant. So rather document and one of the pages related to the um surety for the contractor was inadvertently and then thus adds that page back.
MarianoRight? Questions? Motion move approval and ever change.
OakleyMark was second.
MarianoMotion by Commissioner Mariano, second by Commissioner Oakley. Madam Clerk, please call the roll.
OakleyDistrict One, Commissioner Oakley. Bye. District three, Commissioner Starkey. Aye. District four, Commissioner Weightman. District five, Commissioner Mariano. Aye. District two, Chairman More.