UTD-27-0040
Published agendaHeard once, at the Board of County Commissioners on Oct 20, 2026.
Official title
Amendment No. 1 to the Progressive Design Build Agreement – Vogel Bros. Building Co. – Land O' Lakes Wastewater Treatment Plant Rehabilitation and Expansion (PCU 22-018.00) – $142,099,260.00
Every appearance1 of 1 are in a recording
TranscriptWhat was said at each appearance is below it. Machine transcription, with speaker names inferred from voice matching. 100% of 7 lines carry a name. It shows what was said, not what was decided, and both the words and the names can be wrong.
- 12mJack MarianoChair
And I just pulled this item. This is a progressive design build agreement with Volga Brothers of the Land O' Lakes Water Treatment and Rehabilitation Expansion. Now what I wanted to bring out was as we always hear that you know the counties spending so much money But utilities are an enterprise funds alone, but the number of dollars that it takes to go build this because of new treatment conditions that are put in drive up the cost dramatically. And if you would just talk about what burden
our people are being faced with because of the water treatment, I'm not saying it's bad. I'm just saying it's reality to when you increase the conditions, which I think is good for the environment. But there's a cost to it, if you would address that for us.
Adolpha GonzalezThank you, Mr. Chairman. Good morning, Commissioner. Adolfo Gonzalez, Utilities Engineering and Contract Management Director. This is a an amendment to the Progressive Design Build Project for the Land O' Lakes Wastewater Treatment Plant. This amendment is to initiate the construction phase. The total contract amendment is $142 million. Of that $142 million, approximately $26 million is for new regulations that have been implemented since the construction of the existing plant that's there. Of the $142 million, about three quarters of that
is to upgrade and rehabilitate the existing plant. And another quarter, about thirty-five million, is to provide for additional or future growth or new capacity. That plant right now is permitted at three and a half million gallons per day of capacity. We're gonna add another million and a half gallons of day of capacity for that system.
Jack MarianoChairYeah. Thank you very much.
Kathryn StarkeyMove to approve. Second.
Jack MarianoChairAll in favor say aye. Aye. Aye. All right. Thank you very much.