Zoning Amendment (Consent) – Cherry Hills West MPUD Master Planned Unit Development – Veterans of Foreign Wars of US Major Francis E. Dade Post 4283 et al/ – A Rezoning Request from an A-R Agricultural Residential District to an MPUD Master Planned Unit Development District to Allow for the Maximum Development of 160 Single Family Detached Dwelling Units
What the county recorded
Staff recommendation
Approval with Conditions
DispositionContinued
Approved to continue the item to the March 12, 2024 Board of County Commissioner meeting at 1:30 p.m. in Dade City with Commissioner Bradford absent from the vote.
The source document
The county’s agenda for Board of County Commissioners, Jan 9, 2024
The published PDF, as served by the county. This item is one entry in it.
The county’s minutes for Board of County Commissioners, Jan 9, 2024
The published PDF, as served by the county. This item is one entry in it.
This case, across meetings
PDD-24-7726 in full →PDD-24-7726 was taken up 3 times between Nov 2, 2023 and Jan 9, 2024, continued 2 times — this is appearance 3.
- Nov 2, 2023PlanningPC6▶No disposition in the minutes
- Dec 5, 2023BoardP74▶Continued
- Jan 9, 2024BoardP71▶Continuedthis item
No appearance of this case has a final disposition in the minutes. It was continued, or the minutes do not dispose of it in writing — which is true for 24% of items.
What was said
Machine transcription of 40m of recording, with speaker names inferred from voice matching. 92% of 273 lines carry a name. It shows what was said, not what was decided, and both the words and the names can be wrong.
Okay, P seventy one was advertised in the Tampa Bay Times on October eighteenth, twenty twenty-three.
Is is there anyone
There are individuals signed up.
So are they against this project?
Yeah.
Do you want a presentation first? Do you want a presentation on that? Yeah,
well
presentation first.
Good afternoon, William Vermillion Planning and Development. Uh this is item P seventy one, Cherry Hill's West MPV. uh PDD 247726. This is a general location map in the county of where this project is located, right outside of Dade City. This is a zoning amendment from agricultural residential to master planning development to allow for a maximum development of 160 single-family detached units on approximately 34
acres. It runs alongside VFW Road, approximately 275 feet south of County Road 52.
Here is the aerial location map.
The existing zoning map showing AR.
The future land use map indicating Res 6.
Here is a contextual map to show the overall location. uh the subject site in its proximity to Dade City, Saint Leo and that school there on County Road 52.
Here is the master plan for this development. You'll notice the the VFW will not change in any way. Um It will not change along with this development. It had its club license and alcohol license approved by the Board of County Commissioners in 1975, and that runs in perpetuity with the VFW.
Utilities for this project will also be provided by Date City. And with that, this comes to you with a recommendation of approval with conditions from Planning and Development and the Planning Commission.
Who's util who's providing utilities?
Uh this will be Dade City. They're in the Dade City service uh area. And prior to site plan, they're gonna enter into agreement with Dade City to make sure they have all the capacity.
What are the neighboring log sizes?
So the neighboring lot sizes
What number size is?
There are we zoom out here. Uh across the street you have Abbey Glenn, which is fifties and sixties at a higher density that's proposed here. That's right under six uh dwelling units per acre. This one comes out to be about four point six nine dwelling units per acre. Uh additionally, uh you can't see it here but To the east of Dade City there's another development uh that comes in at seven hundred dwelling units on approximately 150
acres, which is also roughly four point six dwelling units, and that's also your forties, fifties, and sixties.
Okay, I have a question. Uh Ms. Leighton, do you mind? Go
ahead.
Um so where is this in relation to the Orange Belt Trail?
Uh this is um east of
No I think the Orange Belt Trail comes into Saint Leo and
then turns up fifty two I think this is east of Happy Hill Road if I'm not mistaken on County Road fifty.
Right. So that's Smith Road right there running parallel to Saint Leo and then Prosser Road is your other north and south that connects to County Road. I really
need to see that as part of the application. I think we we need to have that to be on the application. Where is it in proximity to the to, you know?
But this is important County Road 52 and it's east of uh Happy Hill Road.
This does not uh the Orange Bell Trail does not run along this portion of the development.
It stops on that year.
And they proceeds north.
So it goes north? Yeah. So are there no campy hill isn't
it?
So are there no plans to continue along this road to the high school or anything, or we're just gonna go to a regular sidewalk after that?
Well, right now this is just the uh the two lanes on County Road fifty two and it's only a hundred feet of ride away right now, so I'm not sure
I just someone needs to start looking at this stuff or I mean we need to have a plan. 'Cause this
we are looking at them Commissioner, but this only has a hundred feet. Uh so if there's gonna be a a larger application of a trail or a sidewalk system This would not achieve much of that network.
Well,
you
know what, I think the orange belt is wider, is is it's like the Penellus trail, right? It's it's a wider trail. It's your main spine. But your feet are network to it. D while it doesn't have to be as wide as that, it shouldn't be as wide as that. It should be more than a sidewalk because people are gonna wanna get to it. So you just need to have Some kind of plan.
along a road like that. as development comes in. So I think it should be more than five feet. Do you have five feet right now?
Yeah.
Nothing?
Yeah, uh it would be required by the Land Development Code. As it exists now, there's nothing because it's just that two-lane road and there's a pretty substantial slope on each side of the road that's being used in training. There's a lot of things.
So you're ready when it comes when that opportunity comes.
I see your county engineer walking.
The well the the part of that uh fifty-two on the north side there is is slope. There's no land for uh for walking on the
Walk Martin on the south side?
Possibly could be sidewalks on the south side.
I mean Otherwise any kid that lives in there is gonna have to drive to school. Or Mm. Or how are they gonna get down to Saint Leo Commons? You know, it's is there an You need some kind of mobility on the side of that roof. You don't want people in the road in State Road fifty two, County Road fifty two walking or writing or pushing a stroller or whatever.
Yeah. That's something we're going to have to take a look at 'cause there's nothing from that point on in toward the high school. After the high school there's some sidewalk, but nothing I'm not sure. There may be some sidewalk at at the fairgrounds.
Yeah.
And that would be on the south side of Fitch II, County River 52.
Question, Chairman
question yes.
Thank you Chair. How how did you come up with Res 6?
Uh I d I didn't come up with res six the comprehensive plan did. That's just the the current future land use for this area is residential six.
I mean that's I'm not
That's that's not what the neighboring properties are throughout here, is it?
Yeah, well I mean I I just mentioned the those neighborhoods that are at a higher density or equal density, just on the same road as this. As well as the surrounding area is also res six.
There are some smaller home lights there on that road, so
Mr. Chairman?
Yes.
We get Dayton City right on the border of it, and we've seen what they've done. Oh yeah, they're annex it
and sell all the dirt off.
And put a put put more density on it as well, so.
We need to have a discussion with them by the way.
Did um did you did our county engineer want to say anything?
This was all red sex.
Because
that's the only designation that's being shown on this planet. Good afternoon, Nick Uran, County Engineer. Um we're in the middle of the P D and E study for Orange Developed Trailer. So we definitely want to construct a facility that will provide the connectivity that you're envisioning. Uh but we haven't nailed down any of the details yet.
Yeah, so if we approve this without any consideration of making sure we have something on the north, we've shot ourselves in the foot. So I would wanna make sure that we have. I that the uh that we have something.
What so? Sorry.
See that to your left is this is the north side, to the right is the south side.
And there's there's a sidewalk there. And then what? It just stops?
Well it runs across that business right there, which is Not a busy area there. I don't know where this does the sidewalk continue on down the road? Do we know?
Doesn't look like there's any there.
No no there's a little one. It's the old fashioned four foot.
Okay.
And I I think that's the right-of-way.
So that goes down probably to that station I'm seeing up on the right.
I don't know if it goes past. Oh there it is. Yeah.
So so So
it's on the south side of County Road.
Well I see one on the north side too.
Well probably where it can be like that, it is, but then where it's really sloped there's no room for
recycling. So I just It's just kind of calling out that what's the plan. And so we need to know what we want that to look like in the future and just slowly arrive at our vision.
Well that sounds like from what Mr Erin says that we are doing the P D and E study to figure out where we're going to align said trail. We don't have that answer today. Um but
you
know,
Okay, but I don't think this is where we talked I think the orange belt turns north before here on the proposed alignment, is that right? No, it doesn't go up Happy Hill now that I'm thinking about it.
I think it's on this court. On the north side. I I think the board right now envisions it being on the north side of County Road
fifty
two.
I think it's on the north side here, actually.
Well the PDE provides options, right? And alternatives, so it it may or may not until the board finally adopts it when when it's complete. So
Well I'd love for it to go into San Antonio. I think the people are gonna ride there anyway. But um I just think that when developments come in They need to show proximity to even if it's the proposed route. So that we We're not hurting ourselves. You know, we sold off we sold off that railroad right away. That we should never have. And I asked it to stop and apparently some were
still going through. So um Com I think Commissioner Mariano wants to say something.
I'm just gonna say it w it's gonna be what, a five foot sidewalk sidewalk now or four foot?
It's four foot, I think it's the old kind.
For that hundred feet just may just ask him to put an eight foot in.
Yeah, or just uh just even reserve the right to get it if we need it. That's that's what I'm saying.
The applicant said they're they're fine adding a condition reserving that right for that for the eight foot on the uh specifically on the part along County Road fifty two that they control.
I think the orange belt's wider than eight foot, but anyway.
If i if if it's an additional eight foot to a four foot then you got the twelve. So
Okay. Are you
questions answered?
Yeah, that was my question. Okay.
Uh let me make a motion for approval. Public over here. You got applicant
presentation, you got public open.
Do you want to do the applicant first or
Yeah. Applicant first. Yeah.
Thank you. Shelley Johnson, 6400 Madison Street, and I have been sworn. I am the applicant's representative. We uh obviously support the staff's recommendation of approval as well as the Planning Commission's recommendation for approval and All of the conditions as well as the additional um condition that was just added. We have no issues with that. Um but I am here to answer any questions. I know that we do have a couple um residents here that had some questions that live you know down the road. So I'm here to answer questions and so is our traffic engineer. So Okay. All right.
Okay, you have two individuals signed up. Mary of McKnight, then followed by Irene Losat. Um and when you come to this the podium to speak, please state your name and address and whether or not you've been sworn.
Yes, I have something I hope to that you will approve to receive and file.
Sorry.
All in favor say aye. Aye. Aye. You can hand it to the class.
Thank you.
I have been sworn in. My name is Mary McKnight at [address removed]. Before the November second Planning Board meeting at which this project was passed, there had been no valid proof that a public notice sign had been posted on Cherry Hills. I want Cherry Hills heard again by the County Planning Board of County Com To allow citizens a chance to voice concerns because if they hadn't known about the project, how could they have come
to speak? Last October I traveled up the BFW road. Uh Dade City had mentioned that Rolling Hills 2 was under the planning process, and I know finding access points can be an issue. So I assume that Erin Likens was trying to find another access for one of her projects contiguous to this. But on that visit I noticed there were no public notice signs. I call Mr. Vermillion to say that Aaron had failed
to post any signs. And I was totally surprised when he told me that Aaron Likens was not involved at all. Now a surprise because the folks at the VFW said they were selling Erin Lycans the lot across the street. Uh Beacon Civil Engineering did the plans for the project. She is their registered agent. The entity requesting the plans for Cherry Hills was Quill one one five, for which Erin Likens is also the registered agent. And
she has every right to be involved with this project, but her name is strangely absent from the paperwork. At any rate, the neighbors said they'd only heard about this project from a Facebook page. Mr Bromillion produced a copy of an affidavit attesting to the fact that the signs were indeed posted. The top page of my handout to you shows this affidavit. At the top it says Lori Burkaw, authorized representative. I assume the county has documentation showing
that the named applicants, the PFW and the Trust, have indeed made Laurie Burkhaw their authorized representative. Secondly, there's an X under the attachment section indicating that a photo of the sign was attached to this affidavit as proof of posting, but no photo was attached. Now this is the most inter disturbing part to me. The notary of this affidavit was Aaron Likens. Sort of statute explicitly stipulates that a notary public may not
notarize a document of a spouse. Flori Burkaw is Erin Lycan's spouse. Nor can she notarize anything for which she has a financial interest. She did both. This rendered the affidavit totally invalid. This was pointed out to Mr. Vermillion. As I understand it, the county asked Beacon to provide another affidavit one that was properly notarized. Right away a sign did appear and Mr. Brumillion received
a photo of it. although it has been face down on the ground since that day. This all occurred after Cherry Hills West had been approved under the Planning Board consent agenda. One last paragraph. I asked that the process be started over at the Planning Board stage. Not one person may show up, but that is not the point. The point is that this board shows citizens that it respects their right to proper public notice and that the commission demands integrity and professionalism
from all stakeholders. Thank you.
Thank you. Next person.
All right. Irene Losat.
Again as you approach the podium name and address and state whether or not you've been sworn.
Irene Losat, [address removed]. I actually am one of the sworn? What? Have you been sworn? I have. Okay, thank you. Thank you. Um, I am actually one of the neighbors that lives in one of the neighboring uh right around the corner from this development. I don't necessarily oppose this uh project. However, I have to agree there was no notice. Um I spoke to Vermillion
several times about the noticing issue. Um I was one of those neighbors that saw the post on Facebook showing that there was going to be a planning board. Um there was no sign. I drive by that the VFW every single day to go back and forth to work. There was no sign. The minute that I mentioned it to Mr. Vermillion, the very next morning I spoke to him and I said, Did you happen to speak
to um the applicants? And he said, Yes. I said, Well, 'cause now there's a sign. The sign appeared the very next day after he spoke to them. That sign is today still laying on the ground. The problem that I have with this project is it's so congested in that one area with Abbey Glen across the street, you've got Heritage Hills on the other side. You have the Sheriff's Office substation right
there. The forestry department us trying to get in and out of our neighborhood, you've got the fair and you got Pasco County High School. All of that, there are times when the fair or anything is going on at that time, we will be sitting there for an hour or more waiting to be able to get into our road to go home. after we've worked all day. Adding more in that area. It
it doesn't make sense to me. Another thing is if this is to be approved, we are requesting or I'm requesting that the stub-outs be removed. that something in the documents would require that the stub outs from Cherry Hill not be allowed to go into the subdivision of Rolling Hills. Well that may may I well isn't a common time. I'll speak after it. Because we
have a legal easement that is our ingress and egress that right now it's on appeal with the city of Dave City. So that has not been decided as of right now. So rather than uh we would just like to eliminate those stub outs so we wouldn't have the traffic coming through our easement. That is our ingress and egress that's on our deeds. Thank you.
Okay, thank you. Anyone else to speak to this item?
See another one applicant comport on it. Got a question.
And I'll have a question after that. Mr.
Chairman Mariano.
Oh, I didn't see 'em coming forward.
Can you give your name and address and state whether or not you've been sworn? Jen Kerouac, [address removed]. I just happen to know you have been sworn? Yes, I have been sworn. Thank you. Thank you. Okay. Um I just noticed um according to and I I could be wrong, uh, but 158.185 purpose of an MPUD uh shows a requirement of fifty acres. I just noticed this acreage was thirty-four, so um I just
wanted to point that out. It looked as if it didn't meet the requirement for an MPUD.
Is I don't know the answer in that.
Denise.
Well, thank you.
Denise, can we answer that?
Hm.
Is there anyone online?
Yeah, was there anybody in there?
Okay.
I'm just curious, uh is this a for sale housing development?
I'm sorry, what was that?
Is it a for sale housing development or is it a rental?
Um I don't know that there's an end buyer right now. Um because they haven't even I mean they're just going through the MPD process just like you know the other developers so um I don't know that there's an end buyer for this property right now, but it is a mix of the forties, fifties um you know lot size which is what this area is developing out around. I did actually I do have a Um and Exhibit if you want to see it that kind of shows you all the stuff that's going on around this property. But immediately I'd like to see the productivity of the roads. Immediately adjacent to the property is um Rolling Hills
One, which is in Dade City, and that's I I think William mentioned it, it's a seven hundred unit development with forty, fifties and sixties villas and townhomes. So um and they have access coming out on County Road fifty two.
Are the are they are they rental?
Uh no, we don't have it's uh Lenar is the who is potentially buying that property. But we d that there's no we haven't closed on that property yet, as far as rolling hills.
So one of our rules and you know, th this is where we get in trouble when people say don't let them connect, then everyone is out on fifty two and no one can go anywhere. So we have to have connectivity um between a in a grid system around community. So what is the grid system around this?
So Rolling Hills right now in the conceptual or not I'm sorry um Cherry Hill on the conceptual you can see that um we have stub outs to the north or to the east, to the west and to the south.
I I only see this. I don't have anything else. Yeah. So it's like it's on the MPD plate. Oh yeah, that was that that other one, right? That was Jones.
Um the stub out to the east that will go into Rolling Hills One, which is that development I was just telling you about, they have access going out to County Road 52 and that is going to be a signalized intersection. Um so you'll have that access, which this will then be able to connect to, as well as the um access that it will have on County Road 52. Okay, very good. And then of course we just get for Western County Hill.
That road that's at the top of it, it just goes to the property line. There's no arrow. What is that? That's what you said.
The road that's on top of
the the north so see where the arrow is that goes to rolling hills and it Next and the dates it's a
Yeah and w that would
be to
the east.
There's a road to the north of that. Yes. It has no arrow. Does that go does that is that a road that will one day maybe continue?
Yeah, it will continue it it'll be connected into Rolling Hills and then Rolling Hills comes out on state road around County Road 52 at a signalized intersection section about a half a mile um west of the or east of this property.
Okay, and then the one connection to the west is future roadway there. Okay.
But the the access to this goes through another neighborhood?
No. So we have access on County Road 52, which is what's shown right here. On this MPD. Yeah, but ca the staff did request that we provide stub outs to the west, which you can see that one have to do that. The east, which the east is where Rolling Hills is, and then to the south. Um and that east access actually will that that Rolling Hills, which is in Dade City, that development, that PD actually has another connection, it's signalized out to County Road fifteen. You too. Um so you'll
have that and then you'll have Happy Hill. So you'll have, you know, breaks in the signalization, but that is um the plan. That there will be connection with there. with that other development. Um there was a question about the affidavits. Um I didn't do the noticing but the affidavits have been provided. We did confirm with staff. Um the pictures were provided. My understanding from one of the residents who just came up to me while I was sitting there, I guess someone keeps pulling the sign down and he keeps putting it back up. um the m one of the members from the VFW. Um So
but the the posting, the affidavit, everything was provided as, you know Um So I don't know why they don't know. Do you guys have to take a photo of it when it's put up? They did, yes. They my the Beacon Engineering did it and they did provide the county a a photo of it. As long along with the affidavit saying that they did their mailing. So I'm not really sure why the assertion's being made that the noticing wasn't done, but was
this project presented to uh Dade City?
No, it's not. I think we've talked I think there's been I let me reiterate. Let me let me restate. I think we've had conversations that this has been talked about in relation to Rolling Hills and that we have it with the county, but no, we didn't we have never um submitted anything to Dade City for this development.
Yeah, no we haven't.
Right. No.
It's It's right on the boundary, but no, it's always we've we've always been in the county on it, so
Hmm. Any other questions?
No, I just wanted that um to talk about the importance of connectivity because if every neighborhood only had fifty two to to move around in, it would be a parking lot. So um we've made the mistake before where we cancelled the connectivity. But it's much better if you have as many as possible for everybody.
If there were a crash on fifty-two. Like it should be. Get somewhere You could go through that. You know, we had a crash on fifty four. W well we had a a truck dump oil. cooking oil on fifty four and no one could go eas or west. Because there's no road going east to west, but stay road fifty four. So no one could get home, no one could get to these businesses, they lost it on the right. Yeah.
I think that was the only issues or questions was the public noticing and so I'll be happy to answer any questions though.
So was it corrected about the uh notary and and then it's a fact that a notary came Can't notarize or uh you know up to the
right-of-way. Yeah, my understanding is that is correct and ultimately. Is that
still the way it is? I mean,
no, I f they fixed it. My understanding is that that when it was brought to the county's attention they had the Applinco go back out and fix the affidavit and they had someone else notarize it. But the posting as required for noticing for the public was in fact done. And they they did provide that proof to the uh county staff.
I don't I just have an uneasy feeling about this project for some reason. So yes, sir. Mr. Weightman.
the variety of reasons that we're talked about here today. I'm uneasy about 160 units or 34 acres with no connectivity. Everybody bottlenecking out in 52 with the project with the with the development across the street. Just I'm not sure if the if the densities that are proposed here or the right fit. And I understand Commissioner Mariano's point about the city date city annexing it in and
what they what they would what they would put on there. So it's kind of like worry I don't cut and then the connectivity point to Commissioner Starkey. No
it needs the connectivity, yeah.
It's
like what
almost
it's got a lot. It's got four and cut the deck here.
If you see the exhibit in uh we put it up um that I identifies all the existing surrounding development. Um like I said, Rolling Hills One is 700 units, uh 50 60s townhome villa. I know that Abbey Glenn's got 40s in it. Um and Rolling Hills 2, which is pending with Dade City right now, is going to be similar uh it to Rolling Hills One with regards to the lots and the mix of uses.
I I I I'm concerned that this board making a decision today would compound Dade City's potential problem. Yeah.
Where is Happy Hill on this? It's to the west of the
big to the west of the easy.
Is Summit View the Dade City One where they took off all the dirt?
I can't be
able to do that.
So there is i uh it actually if you look at the larger aerial, I don't know if there was an aerial in the PowerPoint, but if you look at the arger larger aerial you can see that this area is kind of surrounded by all this approved development that's coming online. So it's actually kind of an infill um with regards to what's actually going on, you know, gonna actually physically be going on on the ground around those properties, around this particular property. So it kind of sits in the middle of it all?
So our our our minimum lot size we adopted the roll but it's forty five feet with sidebar set max at what seven feet?
Dade C Dade City's is fifty.
Uh Good point, Chairman Mariano. When when was this come in because this project doesn't even seem to be in compliant with our our rules during the community?
Um it does have the condition in there that the board adopted. I don't know when um when Beacon filed this particular project, but it does actually have on if you look at condition 37 and 38, it actually has the county's position with regards to if we go above 50 percent on the 40s um that we have to actually do. Do the b the the rear load, you know, all that good stuff. Those conditions that you guys require are in the actual approval. So we are in compliance with the easy thing.
The conditions that we did have from it are the overall lot standards for the fifty foots that we saw, but they still were able to get the forty foot lots because they got those first round comments prior to the PM twenty six.
Okay, this um Who's gonna provide uh water and sappate to this to this project
of motion? Yes, that'll be Dade City.
Do you have that approval? Because the s the reason I'm asking is right now Dade City is uh cut several projects off their list right now on ho and put 'em on hold because they do not have capacity for For sewage or or water at this time.
So Rolling Hills One, this this big development next to Cherry Hills, this one, um we actually have the capacity reserved. We have um we've already done that. We have our an approved USA with Dade City. We're one of the few big developments out there that do. Um so we have that capacity. So um I've had conversations with the city attorney um depending on timing when this thing would come online, you know, whether we could potentially pull from some of that Rolling Hills capacity, you know, and and work out some type of a situation like that. But right now we have service to the
property adjacent and so there's potentially for us a little bit more capacity to get a hold of them maybe. Um some of the other developments that are dealing with that right now. But I am we are aware of of the issue for sure with w with regard to wastewater.
Mr. Chairman Mariano make it for the record since it's being discussed. The only record our office has of the advertisements is being advertised in the Tampa Bay Times on October eighteenth, twenty twenty three. Um and it was advertised for December fifth and it was continued from that meeting to this meeting. So I just that's the only thing our office has of of proof of advertisement. Right. Just so you know.
Okay.
Well does
Does the staff file have revised affidavits of of posting and the the other issues that Ms. Johnson has indicated have been revised?
Yes, absolutely. We have the revised affidavit as well as the photo of the signed posting. You just provide them to the clerk's office? No. So I made this agenda packet prior to receiving the direction to include those. Okay. And I I have them in the stat file on the G Drive and we can pull them up on the screen if you guys would like. As long as as long as the county has them in the official record, absolutely. We also have copies of the certified mailings.
So you will provide them to our office?
Absolutely.
Thank you.
Okay.
Well I I don't know, I still have an uneasy feeling about this this property or this this position. Mr. Waitley.
Thank you. Yeah. You know something's gonna happen here whether City of Dade City annexes it or or not. So I think it's in the best interest of the county to make the right decision here. Um based on the number of units, I think we might consider either be willing to to make a motion to continue this item, maybe reconfigure the lot sizes on here, maybe move to you know the minimum lot size of in the 50s and keep your keep your uh options going
on up from there um and then then bring it back once we see something that might be a little less dense than 160 single family units on 34 acres. Without any connectivity.
Shelley Johnson again. I just just for the record, if if in fact you want to require all fifties and no forties, I don't think my I my client will have an issue with that, so we'd be fine with that.
So I'm looking to keep the variety, especially the large watt sizes. I'm not looking to to have one product type here and I think the boards kind of let's do it.
Sixties?
I think uh whatever tend I'd say we give move make a motion to continue and they come back with that type of direction from us and we we see it again.
Yeah, I'd like a little more time myself to look into it a little more.
That's fine. We're fine with that if you want to continue it. I have no issue with that. We can talk more further about
it.
Uh would you continue to H you do it to a time certain the next The next state city meeting would be Three February.
February sixth at one thirty.
Don't go past that. So don't Dade City Damnex.
I'll make a motion to continue the stuff you said February sixth.
February sixth at one thirty
or
soon there after February sixth
at one thirty with um
Different plan I guess you could say. Well
they've got the subject.
May I say something? I don't know that that gives us enough time to meet the deadlines for the agenda processing. The February sixth.
I don't have the list, but I'm I'm sure it's very it's very soon.
The next one would be um March twelfth. That the next one that's on this side after February sixth.
Why don't you just pick a number that's less than what they're they've got and let them figure out how to lay it out in it? So what is it one six a hundred and sixty units?
So why don't you do it's all say a hundred and thirty units or something?
Won't you let the developer decide?
Yeah, decide the mix of the size of lots, but just cut down make it less dense.
I think there's other issues. when we discuss um in that area and I I have concerns about it right now. So continue would be better for me.
Mr. Chairman? Yes. And I I mean I'll I'll go with that but I just want you to really consider the borderline properties Dade City, Dade City will hop over, they'll move over. They'll probably go this through. If you don't approve it even to what you want, whether it be fifty six without even stating a number yet, um, I think you jeopardize it going, especially now that we can't do it in February we've got to push it back further. They may get frustrated and say, you know what, we'll just go do Dade City, we're done. I really think if you if you really want to get the less density, now's the time to ask for it.
They've got to go to Dayton to do that. I'm okay with that, so
Well. Chairman
Which scenario are you comfortable with, Chairman?
I'm always trying my best to help you.
Well thank you.
Are they talking to you or me?
Can serve read on the project force?
If that's Syria, we're not talking to you.
I'm good with moving it to March.
The first meeting. The first meeting in
March. Back here. No, the second meeting back here.
So m would be March twelfth would be the March meeting and dates, I think.
So amend my motion to continue the item to March twelfth and kind of hearing dates it.
Okay.
And
I'll second discussion. Can I ask the applicant if they're okay with that date?
Yeah, we're okay with that date. So we can figure out how we want to lay it out.
Uh any more discussion? Any more questions? Anyone else here in the audience to speak to this item? See a nine. We have a motion and a second. All those in favor say aye. Aye. Aye. All opposed, like sign. Hearing none. Uh motion passed for zero.