Bass Lake Acres, PVAS No. 3312; Cranes Roost, PVAS No. 3346; Richey Lakes, PVAS No. 3332; Lake Worrell Acres, PVAS No. 3353; and Lakewood Villas, PVAS No. 3354 — Board of County Commissioners — Board Initiated Paving Assessment — No Funding Required

PUBLIC INFRASTRUCTURE - PUBLIC WORKSPW-20-0106District 4

What the county recorded

Published agenda

Staff recommendation

Approve

Approved minutes

DispositionApproved

Approved Staff’s recommendation by roll call vote.

The source document

Published agenda

The county’s agenda for Board of County Commissioners, Jun 30, 2020

The published PDF, as served by the county. This item is one entry in it.

Approved minutes

The county’s minutes for Board of County Commissioners, Jun 30, 2020

The published PDF, as served by the county. This item is one entry in it.

This case, across meetings

PW-20-0106 in full →

Heard once. PW-20-0106 appears on no other agenda in the archive.

  1. Jun 30, 2020BoardR5Approvedthis item

What was said

Transcript

Machine transcription of 10m of recording, with speaker names inferred from voice matching. 65% of 51 lines carry a name. It shows what was said, not what was decided, and both the words and the names can be wrong.

Read it in the meeting →
Mariano

Aye, motion passes five zero. Thank you, Madam Clerk. Now we're going to move down to R5, Mass Lake Acres PVAS.

Unidentified speakerVoice A

Good morning, Commissioner. Azy Caldwell, Public Works. This is a follow-up report for item P W 19. Bash zero one one one storm down the road and five projects here. Lastly, recipe last number three, three, one, two, recipe, number two, three, four, six.

Lake Incorris Pas number three three five three.

Mariano

I gotta stop you. I gotta stop you for a second. Um You're having some technical difficulties. I I think we need to get either move a little closer to the microphone or maybe stop moving around while you're talking one of the two. Can you hear me now? That's so much better. Thank you.

Unidentified speakerVoice A

Okay. Let me just repeat. This is a follow-up report for item number PW 19-0111, storm damage roads. The projects here are Bass Lake Acres, PIVAS number 3312, Cranes Roofs, PASS number 3346, Richard Lakes, PIVAST number 3332. Lake War of Acres, P Bus number three three five three. and Lakewood Villa's Pas number 3354. Next please.

In 2017, the Board of County Commissioners authorized temporary period of storm damaged roads with the condition that public works bring that these projects to the PCC to the board to initiate it. In August 2019, Public Works presented the five projects we mentioned before. uh for consideration by the board so that we could have a board initiate. Next slide, please. The BCC community that agenda item and directed public works to bring the projects back to the

BCC when there was a new pavement contract in place. On May 5th, 2020, the BCC approved a new paving contract. um to APS or Astral Paven System. Next please. And I'll go into each of these projects quickly. In terms of the Basilic Acres project, the total estimated cost based on the new contract is $901,000. I'm just gonna go through the new numbers and off the

right is Ajax with the previous contract. So estimated cost now during $1,133. Maximum cost per ERU is $6,000 and six cents. Discount is $190,783.77. And the maximum cost per ERU after the discount is $4,838. Next, please. Obviously just a location map. Next.

Uh for the photograph of the condition of the road, Bas Lake Drive, Army Avenue, One Avenue, next.

Next, more pictures. And this is Craig's Ruth. Um again. In terms of the current contract, and you can compare it with the previous contract, the current contract $636,785. The maximum cost per PIU $7,8064. The amount of discount is 138,695.78, and the maximum cost after the discount is 6,146,016.

Next, please.

Location map. Next. Work condition next. And this is returned stuff. In terms of total estimated cost on the current contract, $1.8 million. Maximum cost for EIU $5,816.89. Discounted amount is $379,802. The maximum cost for EIU after the discount is $4,612.67. Next

piece. Location map. Pull the graphs of real condition. Mm-hmm. And we go to Lake World Acres. And again, total estimated costs $277,299. Maximum cost per ERU $9,295.01. The discount amount is $96,574.49. And the maximum cost per GAU after the discount is $7,221.26.

Next please.

Location map. foundation or grassroot foundation X Next. And um this is Lakewood Villas and the Estimated cost of language at $59,175. The maximum cost for ERU is $3,793.55. Discount amount is $178,086,066. And the maximum cost for ERU after the discount is $3,094,04. Next

please. Location tab. And will condition programs.

And this is just a quick summary comparison of the projects and the cost per ERU after discount. So you can see the difference in the bottom line there. Under the new contract, the total cost of the project is $4.8 million versus $1.4 billion. Or a million dollars. Um Staff is recommended. Approved.

Thank you.

Mariano

Thank you, sir. Questions from the board at this time.

Starkey

Uh no questions. I just remember when we did chip and slow. It's supposed to be very temporary. So it's taken us a long time to get these. Here, ready to go. So uh Uh, do we have to take a public comment on this?

Mariano

This is not a regular item. We do not take public comment.

Starkey

Okay. Well, um, I would move approval of this of these projects.

Mariano

I have a motion to approval. I'm asking the question.

Oakley

Got a question, Mr. Chairman Mari

Mariano

please.

Oakley

On this APS and Ajax, is this a apples to apple bid? And the lower bid is APS?

Unidentified speakerVoice A

It was complicated. It was compared to bid and um Ajax and APS uh submitted bids, but um APS came out the lower compared to Peter.

Oakley

So we're used we're voting to use APS.

Unidentified speakerVoice A

Well. The projects will be uh used under the APS contract. We're important to have this as board initiated projects.

Oakley

I'm not understanding.

Mariano

We can't under we cannot understand you still. If you can try to get really good, you can't do that. much background question.

Mike Carballa

Commissioner, this is Mike Carbala. Thank you.

Mariano

Yes.

Mike Carballa

Yes. So what the board is voting on now is this is to initiate a board initiated PVAS. So staff will go through the proper procedures to bring back the PVAS ultimately to be to be done. As far as the APS and Ajax contract, staff, like they always do, perform an analysis to see what's in the public's best interest. In this case, doing the work under the APS contract makes the most financial sense.

Oakley

Okay, that's what I was asking. Thank you.

Mike Carballa

Yes, sir.

Wells

How function. The

motion.

Mariano

Okay, I have a motion to make it a little bit more. Chairman discussion real

Wells

quick.

Mariano

Go ahead, Commissioner Weightman. Yes, sir.

Wells

Yeah, most of most of these are in my district. And if you all remember, last year we we delayed these because most of these roads were underwater during the storm. So these are this has already come to us. It's definitely definitely needed. Um the only concern I have have is is with with everything everything going on right now is the is the folks getting hit with this bill. But you know, I I did confirm with Mr. Biles that's going to be. At least a year probably. Is that not correct, uh, Mr. Krabala that you know, these folks. I just want to make sure they're not getting a bill next week for you know, six,

seven thousand dollars, especially with folks being out of work and everything else. So I just want to they need to be done. The residents were in favor of it. I overwhelmingly support the Punch. So I know that's the case, but I just I just want to make sure it's it's going to be down the road a little bit. I I don't think we can get to it until probably 2022. Is that correct?

Mike Carballa

Yes, sir, you are correct. Okay. Thank you.

Starkey

I made a motion. I don't I'm not sure if there was a second.

Mariano

There was. I have a I got it. There was. Mr.

Mariano

Chairman Jack Mariano.

Mariano

Go ahead, Commissioner Mariano.

Mariano

Uh and and Commissioner Weightman, I think we did a great job. And th thank you for your leadership on this one here. By going back out, the average residence in all these bids are saving about a thousand dollars a a head. So that's a lot of money. So we made the right move taking a look at that contract that was out there before to go into this new one. And I think we need to look make sure we keep a look at our our other contract that's out there. Do we need to re bring rebring that one out there to take a look at as well? But uh great work by the team on this one and I I'd be fully supportive.

Mariano

Thank you, Commissioner Mariano. So I do have a motion on the floor by Commissioner Starkey. You have a second by Commissioner Oakley with no further discussion. Madam Clerk, please call the roll.

Oakley

District One, Commissioner Oakley. Aye. District three, Commissioner Starkey. Aye. District four, Commissioner Weightman. Aye. District five, Commissioner Mariano. Aye. District two, Chairman More.