- Aug 26, 2021Planning
PC11No disposition in the minutesPublished agenda
In the room
Transcript4 moments
Machine transcription of 283 recorded meetings — 9% of decided items have one. Speaker names are inferred from voice and can be wrong.
- Utilities planning capacity and development review
Moody So you and you mentioned permitted capacity right now is a little less than uh the actual use is a little less than permanent like maybe a little l less than half of what permanent combat. And so you can transfer between stations. So if for some reason that line does intersect earlier than is expected, you can transfer between different stations. Right. Um you mentioned that was potable water. What about wastewater? Was that that was that was wastewater that
- P11 PEG 247773 Blackwell MPUD zoning amendment
Moody discussion here about Whether or not there's capacity at the Shady Hills wastewater treatment plant, and right now I think utilities position is that there's adequate capacity. I think some previous reports have led us to be suspect of that, but they say it's okay. So
- APC3Zoning Amendment – Evans County Line 80 MPUD Master Planned Unit Development – Evans Properties, Inc. – A Rezoning Petition from A-C Agricultural District to an MPUD Master Planned Unit Development to Allow 300 Multi-Family Units (Platted Townhomes and Condominiums), 100,000 Square Feet of Support Commercial, and 1,500,000 Square Feet of Light Industrial Uses on Approximately 80 Acres, Located South of County Line Road North and East of Lake Iola Road
Moody follow up after. Okay, all right. So I can I ask. Cliff and I I I think maybe address Cliff question. Yeah. if there becomes the necessit necessity to build a private central water and wastewater system How long do you think it would take to get permits from the state to design, build and construct a sizable wastewater treatment plant and then the effluent disposal that goes with it.
- P11 PEG 247773 Blackwell MPUD zoning amendment
Moody Joe, at one time we were told there was zero uncommitted capacity at Shady Hills wastewater treatment plant. But there have been further discussions since that have indicated that that accounting of available capacity was from a legacy