218 in the published record, 4 in the recordings
In the record
Published agenda218 items
Published agendas and the dispositions the approved minutes recorded. Twelve years, whether or not a camera was running.
P57No disposition in the minutesPublished agenda - Aug 19, 2025Board
C39ApprovedPublished agenda Amendment No. 5 to the Professional Services Agreement – Black & Veatch Corporation – Embassy Hills Wastewater Treatment Plant Rehabilitation and Improvements (PCU 16-014.00) – $148,154.00
Approved minutes
Approved the Consent Agenda
- Aug 5, 2025Board
C14ApprovedPublished agenda Task Order No. 4-25 – Arcadis U.S., Inc. – Shady Hills Wastewater Treatment Facility (WWTF) Clarifier No. 5 Repair Services (PCU 22-003.00) – $208,437.81
Approved minutes
Approved the Consent Agenda
- Jul 15, 2025Board
N95ApprovedPublished agenda Revision No. 1 for Task Order No. 04-24 – Professional Service Industries, Inc. – Embassy Hills Wastewater Treatment Plant Rehabilitation and Improvements PCU16-014.00 (UTD25-0316)
Approved minutes
Approved as part of the Public Hearing Consent Agenda.
- Jun 17, 2025Board
C37ApprovedPublished agenda Change Order No. 1 – Titan Construction Management LLC – Shady Hills Wastewater Treatment Plant (WWTP) Clarifier No. 5 Condition Assessment and Repairs; Time Extension (PCU22-003.00) – $193,075.00
Approved minutes
Approved as part of the Consent Agenda.
- May 6, 2025Board
N51No disposition in the minutesPublished agenda Task Order No. 19 – Stantec Consulting Services, Inc. – Water, Wastewater, and Reclaimed Water Rate Study (PIFBA25-0255)
- Jan 28, 2025Board
C23ApprovedPublished agenda Task Order No. 1-25 – Arcadis U.S., Inc. – Shady Hills Wastewater Treatment Facility (WWTF) Clarifier No. 5 Repair Services (PCU 22-003.00) – $384,412.88
Approved minutes
Approved the Consent Agenda
- Jan 28, 2025Board
C25ApprovedPublished agenda Execution of Settlement Agreement – Florida Department of Environmental Protection – Southeast Pasco Subregional Wastewater Treatment Facility (WWTF), Land O’ Lakes Subregional WWTF, and Shady Hills Subregional WWTF Discharge – $250.00
Approved minutes
Approved the Consent Agenda
- Dec 10, 2024Board
N124ApprovedPublished agenda Revision No. 1 for Task Order No. 3-22 - Professional Service Industries, Inc. (PSI) - Southeast Wastewater Treatment Plant Improvement and Expansion (UTD24-0401)
Approved minutes
Approved as part of the Public Hearing Consent Agenda.
- Dec 10, 2024Board
N125ApprovedPublished agenda Task Order No. 5-24 – Freese and Nichols, lnc. (FNI) – Southeast Wastewater Treatment Facility Permit Renewal (PCU 24-815.00) (UTD24-0410)
Approved minutes
Approved as part of the Public Hearing Consent Agenda.
- Dec 10, 2024Board
N126ApprovedPublished agenda Change Order No. 1 (IFB-SN-22-078) – Archer Western Construction, LLC – Southeast Wastewater Treatment Plant Improvement and Expansion (UTD24- 0384)
Approved minutes
Approved as part of the Public Hearing Consent Agenda.
- Nov 12, 2024Board
N95ApprovedPublished agenda UTD24-0384 – Change Order No. 1 – Southeast Wastewater Treatment Plant Improvement and Expansion-Archer Western Construction, LLC – 08-21-2024
Approved minutes
Approved as part of the Public Hearing Consent Agenda.
In the room
Transcript4 moments
Machine transcription of 283 recorded meetings — 9% of decided items have one. Speaker names are inferred from voice and can be wrong.
- Utilities planning capacity and development review
Jon Moody So you and you mentioned permitted capacity right now is a little less than uh the actual use is a little less than permanent like maybe a little l less than half of what permanent combat. And so you can transfer between stations. So if for some reason that line does intersect earlier than is expected, you can transfer between different stations. Right. Um you mentioned that was potable water. What about wastewater? Was that that was that was wastewater that
- P11 PEG 247773 Blackwell MPUD zoning amendment
Jon Moody discussion here about Whether or not there's capacity at the Shady Hills wastewater treatment plant, and right now I think utilities position is that there's adequate capacity. I think some previous reports have led us to be suspect of that, but they say it's okay. So
- APC3Zoning Amendment – Evans County Line 80 MPUD Master Planned Unit Development – Evans Properties, Inc. – A Rezoning Petition from A-C Agricultural District to an MPUD Master Planned Unit Development to Allow 300 Multi-Family Units (Platted Townhomes and Condominiums), 100,000 Square Feet of Support Commercial, and 1,500,000 Square Feet of Light Industrial Uses on Approximately 80 Acres, Located South of County Line Road North and East of Lake Iola Road
Jon Moody follow up after. Okay, all right. So I can I ask. Cliff and I I I think maybe address Cliff question. Yeah. if there becomes the necessit necessity to build a private central water and wastewater system How long do you think it would take to get permits from the state to design, build and construct a sizable wastewater treatment plant and then the effluent disposal that goes with it.
- P11 PEG 247773 Blackwell MPUD zoning amendment
Jon Moody Joe, at one time we were told there was zero uncommitted capacity at Shady Hills wastewater treatment plant. But there have been further discussions since that have indicated that that accounting of available capacity was from a legacy